The USS John C. Stennis's overhaul and refueling, initially set to be completed by August 2025, has been delayed by 14 months and is now expected to finish in October 2026. According to Rear Adm. Casey Morton, the extended rehaul time is a result of COVID-related workforce and material shortfalls. NAVSEA, meanwhile, says the delay is “due both to mandatory growth work following ship conditions assessments, as well as industrial base challenges.” So the Navy is being pretty vague about why Stennis will need an extra 14 months – and blaming COVID, which is becoming the default excuse across sectors.
U.S. Navy Aircraft Carrier John C. Stennis: 'Out of Action' for More Than 5 Years
The USS John C. Stennis's overhaul and refueling, initially set to be completed by August 2025, has been delayed by 14 months and is now expected to finish in October 2026.